Iteration plan/process
...
- We'll use the internal JIRA for detailed task version management.
- Nicholas will try to create a initial set of tasks and version we can grow over time
Definition of roadmap
- panelLet's initially base this on the IIPC proposed Roadmap to be maintained on the WARC implementation Roadmap page.
JHove2 participation
...
- Initial question and answer from JHove2 team regarding participation.
- Nicholas will ask if we could work on a branches.
GZip and ARC module integration status
- panelMain task is to update the module code to work against the main JHove2 code.
- GZIP is now building. Unit test not all parsing.
- ARC nearly building again.